top of page
Logout
Login
Home
CARE
Autodesk Forma Resources
Autodesk Access Request
Common Office Tasks
Follow These Steps – RFIs
Work Orders & Schedule of Values (SOV)
T&M (Time & Materials)
Upload Submittals
Responding to RFQs in Autodesk Build
Supplements (Change Orders)
Change Requests
Okland Billing Cycle
Bridge
Submitting an Application for Payment (AFP) in GCPay
Schedule
Follow These Steps – RFIs
Work Orders & Schedule of Values (SOV)
T&M (Time & Materials)
Upload Submittals
Responding to RFQs in Autodesk Build
Supplements (Change Orders)
Change Requests
Okland Billing Cycle
Bridge
Submitting an Application for Payment (AFP) in GCPay
Schedule
Common Field Tasks
T&M (Time & Materials)
Finding Activities in the Schedule
Access the Latest Drawings
Finding Items in Your Court
Safety Hazard & Safety Incident
QC Inspections
Creating and Closing Issues
Daily Logs
Sheets
Roadblocks
Schedule
T&M (Time & Materials)
Finding Activities in the Schedule
Access the Latest Drawings
Finding Items in Your Court
Safety Hazard & Safety Incident
QC Inspections
Creating and Closing Issues
Daily Logs
Sheets
Roadblocks
Schedule
Okland's Forma Documentation
Project Home
Sheets
Mobile Device
Files
Specifications
Issues
Forms
Photos
Bridge
RFIs
Submittals
Meetings
Correspondence
Schedule
Members
Reports
Project Home
Sheets
Mobile Device
Files
Specifications
Issues
Forms
Photos
Bridge
RFIs
Submittals
Meetings
Correspondence
Schedule
Members
Reports
Menu
Close
4.0 FALL EXPOSURE CONTROLS
Are these controls in place?
4.1 TRAINED BY COMPETENT PERSON
Competent person trained workers using in fall protection
4.2 SUPERVISION BY COMPETENT PERSON
Qualified person supervised design, installation, and use of fall protection
4.3 IMPALEMENT HAZARDS
No impalement hazards (e.g. poorly staged rebar, uncapped rebar)
4.4 FALL PROTECTION ABOVE 6FT
Use of fall protection for all workers working at 6ft or higher (excluding ladder)
4.5 EQUIPMENT CONDITION
Fall protection on lanyard in good condition (no cuts, tears, stitching gaps, chemical/UV damage, metal deformation or corrosion, impact indicators)
4.6 WEARING HARNESS
Harness and lanyard being worn properly
4.7 ANCHOR POINT
Anchor point selected is acceptable
4.8 HOLE COVERS ARE LABELED
Hole covers are clearly labeled with "HOLE" or by clear visual means (e.g. bright orange engineered cover)
4.9 HOLE COVERS ARE SECURED
Hole covers are cleated and/or secured in place
4.10 HOLE DUST PROTECTION
Visqueen, drywall, etc. used to temporarily protect shaft from dust or air flow; is marked "HOLE" and protected by guardrails
4.11 GUARDRAIL UP & SECURE
Guardrail up and secure within the safety zone of the hazard and meets top/midrail heights & capacities
4.12 TOE BOARDS IN PLACE
Toe boards are in place
4.13 STANCHIONS ARE SECURE AND EVENLY SPACED
Stanchions are secure and evenly spaced
4.14 CABLE SYSTEM TIGHT
Cable system is tight with proper deflection
4.15 LADDER USE
Ladders being used correctly (per Okland checklist)
4.16 LADDERS WORKING CONDITION
Ladders are in good working condition (per Okland checklist)
4.17 WALKWAYS WITH CHANGE IN ELEVATION
Walkways with a change in elevation of 19" or more has stairway, ladder, or ramp
4.18 TEMP LADDERS
Minimum of 1 temp or permanent stair operational for structures of 3-stories or more
4.19 TEMP STAIR SHALL BE FILLED
Temporary stairway and landings shall be filled with wood or other solid material to top edge of pan
4. FALL EXPOSURE
Logout
Login
Home
CARE
Autodesk Forma Resources
Autodesk Access Request
Common Office Tasks
Follow These Steps – RFIs
Work Orders & Schedule of Values (SOV)
T&M (Time & Materials)
Upload Submittals
Responding to RFQs in Autodesk Build
Supplements (Change Orders)
Change Requests
Okland Billing Cycle
Bridge
Submitting an Application for Payment (AFP) in GCPay
Schedule
Common Field Tasks
T&M (Time & Materials)
Finding Activities in the Schedule
Access the Latest Drawings
Finding Items in Your Court
Safety Hazard & Safety Incident
QC Inspections
Creating and Closing Issues
Daily Logs
Sheets
Roadblocks
Schedule
Okland's Forma Documentation
Project Home
Sheets
Mobile Device
Files
Specifications
Issues
Forms
Photos
Bridge
RFIs
Submittals
Meetings
Correspondence
Schedule
Members
Reports
Media Center
Careers
Contact
bottom of page